Retrofits can be expected to take 6 to 8 weeks from start to finish. Installations in new construction typically take longer due to the coordination and scheduling with other contractors. Each stage of a geothermal installation can be expected to take the following lengths of time:

  • Permitting and Design – 2 to 3 Weeks
  • Drilling – 3 to 5 Days
  • Trenching Between Boring and House – 1 to 2 Days
  • Piping Connections – 2 to 5 Days
  • Duct Modification or Installation – 1 to 2 Weeks
  • Electrical Connections – 2 to 3 Days
  • Thermostat Set-up, Zoning Control Programming and Start-up – 1 Day